hinkleyyesterday at 6:35 PM0 repliesview on HN

When I worked in commercial aerospace, before we even shipped live there was an incident with a CERT advisory against the XML package we were using. But the fix was only added to the current major version and we were stuck one behind. It took ~3 of our best problem solvers about a week to get that damned thing upgraded. Which put us behind on our schedule.

This made some of my more forward thinking coworkers nervous because what if this happened after we went live? So we started a repeating story called “upgrade dependencies” and assigned it round robin once a month to someone on each application. Every time someone got it the first time they would ask me, “but upgrade what?” Whatever you want, but preferable something that hasn’t been in a while.

For IP and security reasons we were already on vendored dependencies, so it was pretty straightforward to tell what was old. But that made “upgrade immediately” problematic if fixes weren’t back ported far enough and we didn’t want that live.