> We are trying our best to get into mass production and ship out at most several thousand Pebble Time 2s before CNY [which starts in January].

> Realistically, at this time we’re forecasting that the majority of people will receive their PT2 in March and April.

If the factories close for 3 weeks for CNY, then why will the second batch arrive 2-3 months after the first batch?


Replies

eroheadyesterday at 7:13 PM

Good question! (I am the Pebble founder)

When factories restart, not all of the workers who were working there before actually come back to work. Some of them stay in their hometowns or they get other jobs. This means that restarting the production line actually means retraining people on how to assemble the product. There is also an entire supply chain behind the assembly line that takes time to restart. Think of all the sub-components like plastics, metal components, etc. that need to be built at respective factories. It takes time to ship them to the primary factory for final assembly and test.

After the product gets assembled, there are several stages of testing, like gluing, environmental testing, final assembly test, and packaging, that take time as well. Then the product has to be shipped to the fulfillment center, packaged, labeled, and then shipped out. Each step time, and the process needs to completely re-start after CNY.

show 2 replies
small_scombrusyesterday at 7:14 PM

I may be wrong, but I think they mean ship from the factory to the distribution point so that could add some time between an item being made and shipped to a customer