XorNotyesterday at 9:21 PM1 replyview on HN

Knowing nothing else about him, I like him based on this alone.

I've been in planning sessions where someone would confidently declare something would take half a day, was surprised when I suggested that it would take longer then that since they were basically saying "this'll be finished mid-afternoon today"...and was still working on it like 3 weeks later.


Replies

dgunayyesterday at 9:59 PM

Besides the usual unknown unknowns, I've also seen this happen with tasks that involve a lot of coordination in the SDLC. Oh the PR went up at at 2pm PST? Coworkers in EST won't review it until tomorrow. Maybe some back and forth = another day until it clears review. Then QA happens. QA is heavily manual and takes a few hours, maybe with some false starts and handholding from engineering. Another day passes. Before you know it the ticket that took an hour of programming has taken a week to reach production.

show 2 replies