logoalt Hacker News

mpweiherlast Friday at 9:30 PM1 replyview on HN

Where are you getting 18 cents/kWh? Lazard?

Anyway, even if that were correct numbers, it would misleading on several fronts, as the only new western reactors were unrepresentative FOAK builds, and also troubled beyond just regular FOAK status.

Furthermore, the costs tend to be calculated for the period while they are repaying the loans, so it's mostly capital costs. Once the plant is paid off, the price drops dramatically.

The average build time is currently 6.5 years, median slightly less, trend downwards.


Replies

ViewTrick1002last Friday at 9:34 PM

The currently proposed handout from tax money for the French EPR2 fleet is 11 cents/kWh and interest free loans. Sum freely.

That is with the first reactor coming online 2038 with a perfectly executed project.

I suggest you stop referencing unsourced statistics when the topic at hand is new built european nuclear power.

Edit - toned it down

show 2 replies