ViewTrick1002today at 12:02 AM1 replyview on HN

Paid off nuclear plants produce quite cheap electricity. The problem is that it takes 10-15 years of building and then 40 years of paying $180-220/MWh to get a paid off nuclear plant as per modern western construction costs.


Replies

Retrictoday at 12:33 AM

In terms of pure operating costs ignoring everything else it can look good vs other sources that include all costs.

However, ‘Paid off nuclear’ in terms of construction costs still needs to worry about decommissioning, and their maintenance costs keep increasing every year.

Several power plants have looked at going offline for potentially years and spending billions at around year 40 to get to year ~60 as not being worth the investment. That’s the issue with projecting those long lifespans, the buildings/containment structure/cooling tower may be fine but that doesn’t mean the pipes, pumps, turbines, and control systems etc are still fine.

show 1 reply