logoalt Hacker News

triceratopstoday at 2:48 PM1 replyview on HN

> For wind turbine project from design and planning to operational use-takes approximately 4-7 years.

That's still better than 11-12 years. How long does a solar farm take?

If residents' opposition is rooted in higher power prices, data centers could just pay extra instead until the new capacity comes online. Seems like a cheap way to pay off opposition.

> An offshore wind turbine project requires about 7-10 years.

Given this article is about Pennsylvania, it'll probably take millions of years.


Replies

leonidasruptoday at 3:05 PM

> How long does a solar farm take?

24–48 months, but for a data center that has to run 24/7 you need to also build a gas power plant.

https://www.pvfarm.io/blog/utility-scale-solar-project-devel...

https://globalenergymonitor.org/research/betting-big-data-ce...

show 1 reply