> The tech group has issued a force majeure notice related to the power supply to the project developer, a unit of Blue Owl Capital, after the site ran into permitting delays after rising local opposition.
Since when can failing to get a permit be considered force majeure?
Doesn't majeure specifically denote something large scale and out of anyone's control, such as a hurricane?
We have to account for the fact that Oracle is a law firm with a software branch attached to it.
Investors who (rightfully) see this "force majeure" claim as bullshit will have to drag Oracle through court, and Oracle probably counts on this taking years to get settled.
Oracle is in a pretty bad situation, it’s a desperate move. Their debt is rated just above junk since July. They are completely over leveraged. There is a reason the share price has been trending down so much