TSMC's Arizona fab needs 200MW of electricity.
But even more importantly, they need 2 separate completely independent substation feeds, since a 15 second interruption can cause 0.1B Euro of losses.
Finally, and here is where Europe really really suffers, generally you need these things to be planned, approved and built within a year.